Someone asks for the RAG. You look at a late milestone, a thin contingency and a sponsor who wants “green for the pack”. Ten minutes later the slide is green. The plan is not.
RAG status criteria work when each colour maps to a rule you can compute from plan data, every override is logged, and every non-green status has an explicit road to green. This guide gives you starting thresholds, a one-page Excel-style calculator and a short SteerCo narrative. Treat the numbers as a draft to agree with your board—not as a universal standard.
Definition — RAG status criteria: the agreed rules that turn project data (time, cost, scope, risk, benefits) into Red, Amber or Green. Good criteria are computable, use worst-of aggregation (not averages), log overrides, and require a road to green whenever status is not Green.
If reporting itself is the bottleneck, pair this with how to reduce project reporting time. If money is the driver, see what happens when a project goes over budget.
What RAG Is For (And What It Is Not)
RAG (Red / Amber / Green) is a status signal for decision makers. It is not a forecast, not a risk score on its own and not a substitute for the underlying schedule, cost and issue records.
- Green: within agreed tolerances; no escalation required this cycle.
- Amber: outside at least one soft threshold, or on a path that will breach soon without action; management attention needed.
- Red: outside hard tolerance, or recovery needs a decision the project manager cannot take alone (scope, money, date, risk appetite).
In PRINCE2 language, RAG should line up with management by exception: you escalate when tolerances are forecast to break, not when a slide needs a warmer colour. Your SteerCo pack should say what you need—not only how you feel. See also steering committee basics.
Starting Thresholds You Can Type Into Excel
The bands below are example starting points for a single project reporting weekly to a SteerCo. Agree them in writing. Change them for portfolios, regulatory programmes or fixed-date events. Do not treat them as industry averages—they are not.
| Dimension | Input (example) | Amber if… | Red if… |
|---|---|---|---|
| Time | Days of float on the critical path (or days late vs baseline finish) | Float < 10 working days, or forecast finish 6–15 days late | Float ≤ 0, or forecast finish > 15 days late |
| Cost | Estimate at completion vs budget (including agreed contingency policy) | EAC within 5–10% over approved budget | EAC > 10% over approved budget, or contingency exhausted with further overspend forecast |
| Scope / change | Open change requests affecting baseline | Material changes open without SteerCo decision date | Unapproved scope in delivery, or baseline no longer matches what is being built |
| Risk / issue | Highest open risk score or issue severity (your scale) | One “high” item without an owner and next review date | One “critical” item, or several highs blocking the next milestone |
| Benefits (if tracked) | Confidence that benefits assumptions still hold | Key assumption invalidated; replacement not agreed | Benefits case no longer credible and no reset path |
Overall project RAG: take the worst dimension RAG among the dimensions you agreed to report. Do not average colours. Averaging hides the exception that needs a decision.
The One-Page Calculator (Copy Into a Sheet)
Create one row per reporting cycle. Keep formulas boring so anyone can audit them.
| Cell / column | What you enter or calculate |
|---|---|
| A — Cycle date | Reporting date |
| B — Baseline finish | Agreed baseline end date |
| C — Forecast finish | Current forecast end date |
| D — Days late | =C-B in working-day logic you already use (or calendar days if that is your standard) |
| E — Time RAG | Nested IF from the time row in the table above |
| F — Budget | Approved budget (state whether contingency is inside) |
| G — EAC | Current estimate at completion |
| H — Cost variance % | =(G-F)/F |
| I — Cost RAG | IF from the cost row |
| J–L — Scope / risk / benefits RAG | Manual but rule-based (dropdown: Green / Amber / Red) |
| M — Computed RAG | Worst of E, I, J, K, L |
| N — Declared RAG | What you will put on the slide (defaults to M) |
| O — Override? | Yes / No |
| P — Override reason + approver | Mandatory if O = Yes |
| Q — Road to green | One sentence + owner + date (mandatory if N ≠ Green) |
That sheet is the calculator for version one: transparent, portable and reviewable in a SteerCo pack. An interactive web widget can wait until the rules are stable.
Worked Example (Illustrative Numbers Only)
Suppose baseline finish is 30 working days away, forecast finish is 22 days of float consumed with 5 days of float left, EAC is 7% over budget, and one high risk has an owner and a review this week.
- Time → Amber (float under the 10-day soft band in the starter table).
- Cost → Amber (7% sits in the 5–10% band).
- Risk → Green under the starter rule (high item has owner + review date).
- Computed RAG → Amber (worst of the set).
Declared RAG should stay Amber unless someone with authority overrides and logs why—for example, temporary cost pressure already funded by an approved change that the EAC field has not yet reflected. If you override to Green without fixing the inputs, you are doing watermelon reporting: green outside, red inside.
Override Log (Non-Negotiable)
Overrides happen. Sponsors ask. Politics exists. The failure mode is an override with no memory.
Minimum fields when Declared RAG ≠ Computed RAG:
- Date and reporting cycle
- Computed vs declared colour
- Reason in one sentence (fact, not hope)
- Approver name and role
- Expiry: which future cycle the override dies unless renewed
If you cannot name an approver, you do not have an override—you have a wrong status.
Road to Green
Every Amber or Red needs a recovery path that a stranger can understand in thirty seconds:
- Cause: which dimension tripped the rule
- Action: what changes in the plan (not “monitor closely”)
- Owner: one name
- Date: when the action lands, and when RAG should be re-computed
- Ask: what decision you need from SteerCo, if any (money, scope, date, risk acceptance)
For messy recoveries, the practical reset moves in how to bring order to a messy project sit beside this RAG discipline—not instead of it.
How to Roll This Out in One Week
- Draft thresholds with the project board or PMO (use the starter table).
- Build the one-page sheet; lock column meanings.
- Run one cycle in parallel with your old slide colour—compare Computed vs Declared.
- Agree the override rule in SteerCo minutes.
- Retire gut-feel colouring for that project.
Checklist Before You Send the Pack
- Every dimension has a stated input and rule
- Overall RAG is worst-of, not average
- Computed and declared colours are both visible
- Overrides have approver and expiry
- Non-green has cause, action, owner, date, ask
- Numbers in the RAG sheet match the schedule and cost files you would defend in the room
FAQ
What does RAG mean in project management?
RAG means Red, Amber and Green. It is a status signal for decision makers, not a forecast by itself. Each colour should map to a rule you can recompute from the same inputs every cycle.
How do you set RAG status criteria?
Agree dimensions (at least time and cost), set Amber and Red thresholds per dimension, take the worst dimension as overall RAG, require an override log when the slide colour differs from the computed colour, and require a road to green for every non-green status.
Should you average RAG colours across workstreams?
No. Averaging hides the exception that needs a decision. Use worst-of for the project overall, and show workstream RAGs separately if needed.
Further Reading
- How to Reduce Project Reporting Time
- What Happens When a Project Goes Over Budget
- What Is a Steering Committee (SteerCo)?
- What Are Project Constraints?
- AI in Project Management (2026) — where automation helps status drafting, and where human checks still own RAG
Want the next field note when it lands? Join the newsletter.