One RAID log card with typed rows for risks, issues, assumptions and dependencies, beside smaller Actions and Decisions cards, with the Insights Spotter logo in a navy band

RAID Log vs Risk Register: One Working List, Not Two

By Paulius Petravicius

Monday 26 October, ten minutes before the weekly review. Sam, project manager on the Spotter booking-service trial, opens the RAID log and finds row 14: “Supplier test environment may be late – chase supplier – Alex – amber.” The environment was due last Friday. It did not arrive. Integration testing has already stopped, so the risk has become a problem. “Chase supplier” has no date and no definition of done. And the sponsor agreed a fallback at last week’s SteerCo, but that agreement exists only in the minutes.

Sam and Spotter are fictional. The row is not. Most project managers have inherited one like it, and the usual reaction is to add more tools: a separate risk register, an issue log, an action tracker, a decision record. Then nobody knows which one is current.

In practice, you need one working list, not two. The RAID log is where your risks and issues live, with assumptions and dependencies alongside them when they matter. Keep each type distinct inside that list. Next to it, keep a decision log and an action log on every project, because decisions and actions behave differently from risks and issues. A separate formal risk register is the exception, and you need it when governance asks for it, not by default.

I don’t know a single project manager who keeps a RAID log and a separate risk log going side by side week after week. When both exist, one of them is usually out of date.

Education note

This is a practitioner’s working model, not a standard. PMI, PeopleCert (PRINCE2) and APM do not prescribe “one RAID list plus a decision log and an action log”. The table and rules below are InsightSpotter teaching aids for you to adapt. If your organisation or method mandates specific registers, follow that first.

RAID has two common expansions. Risks, Assumptions, Issues, Dependencies, or Risks, Actions, Issues, Decisions. Both are valid. Pick one per project and write it at the top of the log.

RAID log vs action log vs decision log

QuestionRAID logAction logDecision logSeparate risk register (rare)
What is it?The project’s one working list of things that could hurt it or are hurting it now.A list of agreed follow-ups, each with an owner and a date.A record of choices made, by whom and why.A fuller, controlled risk record kept for governance.
What goes in it?Risks and issues; assumptions and dependencies as needed.Commitments from reviews and SteerCos. Not routine delivery tasks.Approved choices, conditions and rationale. Not proposals.Detailed analysis, response approvals and history.
Time directionFuture (risks) and present (issues).Next days or weeks.Past, kept for reference.Future, often over a long horizon.
How fast does it change?Weekly.Constantly. Rows open and close every meeting.Slowly. Rows are added and rarely edited.On a set review cycle.
When do you need it?Always, on any project worth a review meeting.Always. It’s where follow-ups get an owner and a date.Always. It’s the record of who agreed what.When a PMO, audit, regulator or programme demands it.

Read the table from left to right. The RAID log is the default. The next two columns are the logs you keep alongside it on every project. The last column is the one you should be able to justify before you create it.

What is a RAID log?

A RAID log is a single list where each row is one thing the project has to manage: a risk, an issue, an assumption or a dependency. The value is in having them side by side. In a Monday review you can see in one place what might go wrong, what already has, and what you are relying on.

Inside that list, keep the types honest. A risk is an uncertain event that has not happened yet; it may hit the project or create an opportunity. An issue is a problem that is happening now. PMI’s PM Network piece “Risks vs. issues” puts it in terms of timing: a risk is described in the future tense, “if this happens…”, and an issue in the present tense, “we have this problem”. An assumption is something you are treating as true without proof. A dependency is something you need from outside the team.

One list does not mean one blurred list. Margaret Love’s PMI conference paper “Risks, issues, and changes—help, I’m drowning in logs!” makes the point well: you can track these items in the same log, but because the response to each type is different, you still have to decide what each item actually is. A type column is not decoration. It tells the reader what kind of response the item needs.

For field lists, a ready-made sheet and a worked review, see the InsightSpotter RAID log guide and template.

Education note: PRINCE2 users. PRINCE2 7 has its own management products and a broader idea of an issue than “a current problem”. PeopleCert’s explanation of PRINCE2 7 issues describes an issue as a problem, a concern, a business opportunity, a request for change or an off-specification, and notes that not every issue becomes a change. On a PRINCE2 project, tailor the RAID log to those definitions rather than replacing them.

What is an action log?

An action log holds commitments: “Alex will get written confirmation of the fallback environment from the supplier by Thursday.” Each row needs three things:

  • One named owner. Not “the tech team”.
  • A due date. “Before go-live” is usually too late to help.
  • A completion condition. What evidence lets you close it? An email sent is not the same as a supplier confirming readiness.

Why keep actions in their own log? Because they move at a different speed. Actions open and close at every meeting. If they sit in the RAID log, the list fills up with “done” rows and the risks get lost. Even if your team uses the “Risks, Actions, Issues, Decisions” expansion of RAID, keep the follow-ups themselves in the action log and let the RAID row point to them.

Two limits apply. An action log is not a second backlog. The Love paper is blunt about this: tasks belong in the schedule, and tasks kept in the log give “a distorted view of the remaining project work”. Keep design, build and test work in the plan or the board. Use the action log for the follow-ups a review has asked for. Second, give every action a link back to the RAID item it serves, such as “A-021 → I-009”, so the follow-up can always be traced to the problem.

What is a decision log?

A decision log records what was decided, who had the authority to decide it, when, why, and under what conditions. It is the slowest-moving list on the project and one of the most valuable. Love’s paper notes that decisions that are not clearly documented get “rehashed” months later. That is exactly the conversation a decision log saves you from.

Decisions get their own log for the opposite reason to actions. They do not churn. They need to stay findable long after the risk or issue behind them has closed. A decision buried in closed RAID rows or old minutes is effectively lost.

Two habits make a decision log useful. Record the outcome, not the discussion: “Sponsor approved a staff-only trial, conditional on acceptance checks passing” is a decision, while “discussed at SteerCo” is not. And keep proposals apart from approvals. If you prepare decisions for a steering committee, our decision-focused SteerCo agenda shows how to read back the authority and the conditions before people leave the room.

What about a separate risk register?

Sometimes you do need one. A PMO may require a standard risk format across a portfolio. An audit or regulator may expect scored assessments, approved responses and a retained history. Public-sector bodies in the UK work within HM Treasury’s Orange Book on the management of risk, and a programme may need to roll project risks up into its own reporting. In those cases a fuller risk register is a governance requirement, and APM’s overview of risk management describes what it typically documents: the risks, their analysis and responses, and clear ownership of actions. If you must keep one, make it the authoritative record for risks and let the RAID log carry only the reference, the owner and the next review date. Two independently edited copies of the same risk is the outcome to avoid. For most projects, though, the risk section of the RAID log is the risk register.

Illustrative example: the Spotter booking-service trial

This example is fictional. Spotter, Sam and the team are teaching characters, not a real project or client.

Back to Sam’s row 14. Before the review, Sam takes it apart:

In the RAID log

  • R-014 (risk, closed as occurred). “If the supplier environment is not available by 23 October, integration testing will miss the readiness review.” Owner: Maya. It occurred, so Sam marks it as occurred and links it to the new issue. Following the PMI timing distinction, the item moves from future tense to present tense. Sam keeps the risk history for lessons learned rather than deleting it.
  • I-009 (issue, open). “Supplier environment not delivered; integration testing stopped since 23 October.” Owner: Noor, who coordinates resolution. Impact: the readiness review on 6 November is at risk.
  • R-019 (new risk). “If the fallback environment differs from production, defects may surface only after go-live.” Owner: Maya. This one really is uncertain, so it is a risk.

In the action log

  • A-021 → I-009. Alex obtains written confirmation of the fallback environment’s configuration from the supplier by Thursday 29 October. Done when the confirmation is attached and reviewed by the technical lead.

In the decision log

  • D-006 → I-009. On 22 October the sponsor approved switching to the fallback environment for a staff-only trial if the supplier environment was late, conditional on mandatory acceptance checks passing. Rationale and the SteerCo reference are recorded.

One cluttered row has become five clean ones, each with a single meaning, owner and next step. At the review Sam does not ask “which log are we updating?” Sam asks what has changed. The answer is that I-009 is open, A-021 is due Thursday and D-006 is conditional. Sam’s status report therefore stays amber with the issue named, rather than drifting to green because “an action is in place”. Our RAG status criteria explain why an owner and an action do not make an open problem green.

Completing A-021 will not close I-009 on its own, either. Noor still needs testing to restart. Closing the action and resolving the issue are two separate events, which is why they are two separate rows.

What a project manager should avoid

  • Mixing risk, issue and action in one row. “May be late – chase supplier” is three things with three owners and three closure conditions. Split it.
  • Turning everything into a risk. A missed delivery is not a risk any more. Leaving it worded as “may” hides a live problem behind a likelihood score.
  • Running duplicate lists nobody updates. A RAID log, a separate risk log and a SteerCo tracker that all hold the same supplier problem will disagree within a fortnight. Give every item one home and reference it elsewhere.
  • Letting the letters drift. If A means “assumption” to one person and “action” to another, your log is lying to someone. Declare the expansion.
  • Copying sprint tasks into the action log. Two queues for the same work give you two different due dates.
  • Recording discussion as decision. If you cannot name who approved it and on what conditions, it is not a decision yet.

The review rhythm matters more than the number of lists. Look at open issues every week, review risks on a cycle that suits the project’s length and uncertainty, check the actions that are due, and read back new decisions. Escalate urgent issues straight away, without waiting for the next meeting.

The practical distinction

A RAID log tells you what could go wrong and what is going wrong. An action log tells you who will do what by when. A decision log tells you what was agreed and on whose authority. A separate risk register gives governance a fuller record of risk when it formally asks for one.

So “RAID log vs risk register” is usually the wrong question. On most projects the RAID log is the risk register, plus the issues. Keep one working list, keep the types distinct inside it, and keep a decision log and an action log next to it.