The real challenges behind the project manager role
People sometimes think being a project manager means running around telling everyone what to do. That is only one side of the story. A lot of the work is making a complicated situation visible: what are we trying to achieve, what is getting in the way, who can decide, and what needs to happen next?
I have found that many difficult moments are not solved by working longer or sending another reminder. The PM may depend on people who report elsewhere, a supplier, a decision forum or information that is not ready. The job is to make the situation clear, bring the right people into it and help the project take a sensible next step. The exact authority of a project manager varies, so agree the role and escalation route rather than assuming you can direct everyone.
Here are ten common challenges, with practical ways to respond. They are not a checklist that every project must follow; use the parts that fit your situation.
1. The outcome or success criteria are unclear
A project can have a title, a deadline and a long list of activities while people still disagree about what the work is meant to change. If the sponsor, delivery team and service owner use different definitions of “done,” the plan will not fix the problem.
What helps: Ask the sponsor to confirm the intended outcome, who benefits, what must be delivered, how acceptance will be judged and what is outside the current scope. Write down the open assumptions. If the answer is still uncertain, show how that uncertainty affects the next estimate or decision instead of quietly treating an assumption as fact.
2. New requests keep arriving after work starts
Some changes are necessary. The difficulty is allowing work to enter the plan without understanding what it replaces or affects. A small request can use the same people, time or approvals needed for a more important delivery.
What helps: Capture the request, ask what problem it solves, and assess the effect on scope, benefits, schedule, cost, quality, risk and people. Then recommend whether to approve, reject or defer it through the agreed authority. Update the baseline only after the decision is made. This is a way to manage change, not to stop people improving the idea.
3. The budget or estimate no longer looks credible
A forecast can move because an assumption was wrong, a dependency changed, costs increased or an approved change added work. Asking for more funding is not automatically a sign of poor project management. Hiding the forecast or presenting an old figure as still achievable is more likely to damage trust.
What helps: Compare actuals and commitments with the latest estimate, explain the main causes of movement and show what remains uncertain. Bring options with consequences: change scope, change timing, add capacity, use an approved reserve or stop. The sponsor or funding authority decides what is acceptable within the governance rules.
4. The people you need are shared across several priorities
In a matrix organisation, a project manager may coordinate people without controlling their workload. A name on a resource plan does not mean that person has the time or the right skills available when the project needs them.
What helps: Agree named owners, the level of effort and the time period needed with the relevant line manager or resource owner. Ask what work would be displaced. If the commitment cannot be met, make the effect on milestones or scope visible and take a choice to the sponsor. Replanning is often more useful than repeatedly asking the same person to “prioritise.”
5. Dependencies and hand-offs are not clear
A team can finish its own task and still leave the project blocked if nobody owns the next step. This often happens between a supplier, a technical team and the business area that must accept the result.
What helps: For each important hand-off, record who provides what, who accepts it, what evidence is needed, the agreed date and what happens if it is late or incomplete. Check the sequence with the people doing the work; a date in a plan is not confirmation that the dependency is ready.
6. Meetings do not produce shared decisions
It is tiring when the same topics return in different meetings and the team leaves without a clear decision or owner. More meetings do not necessarily improve communication.
What helps: Give each meeting a purpose. Mark agenda items as for information, discussion or decision. Send the evidence people need beforehand, capture decisions and actions in the agreed place, and start the next meeting by checking only the actions that matter. If the person with authority is absent, record what is needed and when the decision will be made rather than writing “agreed” on their behalf.
7. The team does not have the capability or information it needs
A skills gap may be a training need, unclear requirements, a workload issue or a missing specialist. It is not solved by assuming a team member can learn a complex task while delivering it under a fixed deadline.
What helps: Ask the people doing the work what knowledge and support the task requires. Agree whether the right response is coaching, a specialist, a review step, a change in sequence, or a different scope. If quality is at risk, agree acceptance criteria and who can sign off the work before it reaches a user or service.
8. Stakeholders want different things
Disagreement does not always mean a stakeholder is difficult. People may be protecting different outcomes: speed, control, accessibility, cost or continuity of service. A project manager cannot promise that every request will be accepted.
What helps: Ask what need or risk is behind each position. Separate evidence from preference, identify who has the decision right and show the trade-offs. Consult the people affected when the design is still open. Explain what can change, what is fixed and how the decision will be made. My practical stakeholder engagement guide has a simple way to plan those conversations.
9. Risks appear late or plans assume everything will go well
Risk management is not predicting every problem. It is noticing uncertainty early enough to consider what it could affect and who can do something about it. A list of red risks without owners or responses does not reduce exposure.
What helps: Describe a risk as a possible event and its effect on an objective. Agree an owner, a response, a trigger for action and a review date. Also check whether a response creates a new dependency or risk. When something has already happened, manage it as an issue and decide whether the plan or forecast needs to change.
10. Ownership is assumed rather than agreed
“The team owns it” can sound positive but leave nobody sure who will take the next action. The opposite can also happen: the PM picks up every unfinished task and becomes a bottleneck.
What helps: Give each action one named owner who has agreed to it, a clear result and a realistic due date. The PM follows progress and addresses obstacles, but the work remains with the agreed owner. For a dependency outside the team, ask the sponsor to agree an escalation when the owner or capacity cannot be secured.
A practical example: the release date is at risk
This is an illustrative scenario. The supplier now expects a test environment after the date the team planned to begin testing. The business still wants to keep the release date, and a new compliance requirement has also been raised. The project manager cannot fix all three issues alone.
First, ask the test lead and supplier to confirm the environment forecast and what can be tested before it arrives. Ask the compliance lead what evidence is required and whether the requirement must be met before release. Then update the schedule and impact assessment. The team can continue work that does not depend on the environment while the sponsor considers the release options.
A useful escalation note could fit on one page:
- Current position: what has happened, what is confirmed and what is still an assumption.
- Impact: what the date, cost, scope, quality, benefits or service could be affected by.
- Options: realistic choices, including the consequence of waiting or making no decision.
- Recommendation: the option the PM believes best supports the agreed outcome, with its assumptions.
- Decision needed: who has authority, by when, and what happens if no decision is made.
- Next actions: who will do what, and when the forecast will be reviewed.
This gives the sponsor a decision to make rather than a vague warning that “the project is slipping.” It also protects the team from treating an unapproved workaround as a new baseline.
When the PM cannot fix it directly
Some constraints need action from the sponsor, a line manager, a service owner or a governance forum. Bring them the evidence and the decision needed early. Be clear about what the team can continue safely, what is blocked, and the likely consequence of delay. Keep a record of the decision and update the plan and people affected.
That is not passing the problem away. It is using the authority the project has agreed. If the route is unclear, ask the sponsor to establish who can decide before the team commits to a date or change it cannot control.
Why project management can feel difficult
The project manager works across plans, people, decisions and uncertainty, often without direct authority over every dependency. Some days the role feels like making progress while several things remain unresolved. That is part of the work, but it does not mean the PM should absorb every risk or take responsibility for decisions belonging to other people.
Start with the outcome, make the current position honest, get the right decision-maker involved and agree the next action with an owner. You will not remove every challenge, but you can make it easier for the team to respond before a small problem becomes a surprise.
Further reading
- APM: What is scope management?
- APM: What is change control?
- APM: What is risk management?
- UK Government Project Delivery Functional Standard (GovS 002)
Subscribe to our newsletter!
Latest Blog Posts
- AI as a Team Member: Pros, Cons and How PMs Manage It

- When AI Is on the Team: A Week with Mira

- RAG Status Calculator: Turn Evidence into a Reviewable Colour
- SteerCo Agenda: Put Decisions Before Updates
- Using AI to Draft Status Reports Without Losing the Facts

- RAID Log: Template, Examples and the 15-Minute Weekly Review